How to Draw Gantt Charts in Mermaid

Gantt charts visualize project tasks as horizontal bars, showing start/end dates and dependencies. They are essential for project planning, sprint scheduling, and release management.

Basic Structure

gantt
    title My Project Plan
    dateFormat YYYY-MM-DD
    section Phase 1
    Task name : 2026-03-01, 5d

在 MermZen 中试试 →

Task Dependencies

gantt
    dateFormat YYYY-MM-DD
    section Development
    Backend  : be, 2026-03-01, 7d
    Frontend : after be, 5d
    QA       : after Frontend, 3d

在 MermZen 中试试 →

after id starts a task after another completes.

Task States

gantt
    dateFormat YYYY-MM-DD
    Completed   : done,   2026-03-01, 3d
    In progress : active, 2026-03-04, 5d
    Pending     :         2026-03-09, 4d
    Critical    : crit,   2026-03-09, 3d

在 MermZen 中试试 →

Full Example: Product Iteration

gantt
    title MermZen Blog Feature v1.0
    dateFormat YYYY-MM-DD
    excludes weekends

    section Design
    Requirements    : done,   req,    2026-03-01, 2d
    UI prototyping  : done,   ui,     after req,  3d

    section Development
    Template dev    : active, tpl,    after ui,   4d
    Article writing :         art,    after ui,   6d
    CI setup        :         ci,     after tpl,  2d

    section Launch
    QA testing      : crit,   test,   after ci,   3d
    Launch          : milestone,      after test, 0d

在 MermZen 中试试 →


To try the above code in MermZen, click Open Editor and paste the code there.