How to Draw Gantt Charts in Mermaid

Gantt charts visualize project tasks as horizontal bars, showing start/end dates and dependencies. They are essential for project planning, sprint scheduling, and release management.

Why Use Gantt Charts?

Gantt charts are one of the most intuitive visualization tools for project management:

Basic Structure

gantt
    title My Project Plan
    dateFormat YYYY-MM-DD
    section Phase 1
    Task name : 2026-03-01, 5d

在 MermZen 中试试 →

Task Dependencies

gantt
    dateFormat YYYY-MM-DD
    section Development
    Backend  : be, 2026-03-01, 7d
    Frontend : after be, 5d
    QA       : after Frontend, 3d

在 MermZen 中试试 →

after id starts a task after another completes.

Task States

gantt
    dateFormat YYYY-MM-DD
    Completed   : done,   2026-03-01, 3d
    In progress : active, 2026-03-04, 5d
    Pending     :         2026-03-09, 4d
    Critical    : crit,   2026-03-09, 3d

在 MermZen 中试试 →

What is Critical Path?

The critical path is the longest chain of tasks from project start to finish. Any delay in critical path tasks directly delays the entire project.

gantt
    dateFormat YYYY-MM-DD
    section Critical Path Example
    Requirements    : crit, req, 2026-03-01, 3d
    Backend dev     : crit, be, after req, 5d
    Frontend dev    : fe, after req, 4d
    Integration test: crit, after be, 2d
    Deployment      : crit, after Integration test, 1d

在 MermZen 中试试 →

In this example, Requirements → Backend dev → Integration test → Deployment forms the critical path (11 days total). Frontend dev can run in parallel with Backend dev and doesn't affect the total duration.

Tip: Use crit to mark critical path tasks so the team can quickly identify which tasks cannot be delayed.

Full Example: Product Iteration

gantt
    title MermZen Blog Feature v1.0
    dateFormat YYYY-MM-DD
    excludes weekends

    section Design
    Requirements    : done,   req,    2026-03-01, 2d
    UI prototyping  : done,   ui,     after req,  3d

    section Development
    Template dev    : active, tpl,    after ui,   4d
    Article writing :         art,    after ui,   6d
    CI setup        :         ci,     after tpl,  2d

    section Launch
    QA testing      : crit,   test,   after ci,   3d
    Launch          : milestone,      after test, 0d

在 MermZen 中试试 →

Best Practices

Use after for Task Dependencies

Clearly define task dependencies to let the Gantt chart automatically calculate start times for subsequent tasks:

gantt
    dateFormat YYYY-MM-DD
    section Development Flow
    Requirements review  : req, 2026-03-01, 2d
    Technical design    : after req, 3d
    Implementation      : after Technical design, 5d
    Code review         : after Implementation, 1d

在 MermZen 中试试 →

Use excludes weekends for Non-Working Days

Make your Gantt chart reflect actual work schedules:

gantt
    dateFormat YYYY-MM-DD
    excludes weekends
    section Sprint
    Sprint 1 : 2026-03-02, 10d

在 MermZen 中试试 →

Use milestone for Key Dates

Milestones are key time points in a project, marked with diamonds:

gantt
    dateFormat YYYY-MM-DD
    section Milestones
    Requirements freeze  : milestone, m1, 2026-03-10, 0d
    Code freeze          : milestone, m2, 2026-03-20, 0d
    Production release   : milestone, m3, 2026-03-25, 0d

在 MermZen 中试试 →

Limit Tasks per Section to 5

Too many tasks make Gantt charts hard to read. If a phase has too many tasks, consider splitting into multiple sections or sub-projects.

Common Pitfalls

Overly Granular Tasks

Problem: Breaking tasks down to hourly levels makes the Gantt chart overly complex.

Solution: Use 1-5 days as the minimum task unit. Finer-grained tasks are better managed with kanban boards or task lists.

Ignoring Task Dependencies

Problem: All tasks have fixed dates without using after for dependencies.

Consequence: When predecessor tasks are delayed, subsequent tasks don't automatically adjust, making the Gantt chart unreliable.

Solution: Prefer after for dependencies, and only specify fixed dates when necessary.

Not Marking Critical Path

Problem: All tasks use default colors, making it impossible to quickly identify which tasks have the most impact on project progress.

Solution: Use crit to mark critical path tasks so the team can focus on core work.

Quick Reference

Syntax Function
gantt Declare Gantt chart
title Title Chart title
dateFormat YYYY-MM-DD Date format
excludes weekends Exclude weekends
section Name Task group
Task : Date, Nd Specify start date
Task : after TaskID, Nd Depend on previous task
Task : id, Date, Nd Task with ID
:done Completed (gray)
:active In progress (blue)
:crit Critical path (red)
:milestone Milestone marker

To try the above code in MermZen, click Open Editor and paste the code there.